Opportunities

Design and Construction of the General Project of the Altos de la Cueva Adventure Park, San Miguel

Inter-American Development Bank
Country:El Salvador
Sector: Construction and related services
Start date: Wednesday, September 18, 2024
End date: Wednesday, October 30, 2024
Description

The Government of the Republic of El Salvador has received a loan from the Inter-American Development Bank, granted under the Bank's GN-2349-15 policy, to partially finance the Support Program for the Recovery and Expansion of the Tourism Sector in El Salvador, and intends to use part of the funds from this loan to make payments under the contract: "Design and Construction of the General Project of the Altos de la Cueva Adventure Park, San Miguel."

The Ministry of Tourism invites eligible bidders to submit sealed bids for the design and construction under a lump-sum single-responsibility contract for the "Design and Construction of the General Project of the Altos de la Cueva Adventure Park, San Miguel."

Item Description

Delivery Time for

Final Design

Delivery Time for

Construction of Works

Amount
1

Design and Construction of the General Project of the

Altos de la Cueva Adventure Park, San Miguel

270 calendar days 600 calendar days $8,826,550.00