Execution of work: Temporary Relocation Plan (PRT) of the project "Improvement and expansion of the pedagogical higher education service in I.S.P.P. Azángaro, district of Azángaro – province of Azángaro – department of Puno"
Opportunity details
Description
Peru, through the Ministry of Education (Executing Unit 118 - PMESTP), has financing from the Inter-American Development Bank (IDB) for the "Investment Program: Improvement of the Quality of Higher and Technical-Productive Education Services at the National Level". This call for National Public Bidding (LPN) invites eligible bidders to submit closed proposals for the execution of temporary educational infrastructure works.
Scope of the works
Main objective: Execution of the works corresponding to the Temporary Relocation Plan (PRT) for the Institute of Public Pedagogical Higher Education (I.S.P.P.) Azángaro, in the department of Puno.
Execution time: The estimated time for construction is 120 days.
Qualification Requirements and Conditions
Regulatory framework: The process is carried out in accordance with the National Public Bidding procedures provided for in the IDB's Policies for the Acquisition of Works and Goods.
Evaluation criteria: Accreditation of financial capacity, average annual turnover in construction, as well as demonstration of general and specific experience in execution of works.
Margin of preference: No margin of economic preference will be granted to national contractors or consortia (APCA).
Required guarantee: It is mandatory to attach the Bid Maintenance Statement to the proposal.
Management and submission of bids
Access to the bases: The bidding documents in Spanish can be requested by email to the Executing Unit 118 (adquisiciones.pmestp@ue118.gob.pe) or consulted directly on the institutional web portal.
Delivery method: Bids must be sent in physical form and in a sealed envelope at the headquarters in San Isidro, Lima. Electronic bids will not be allowed and late proposals will be rejected.
Note: Consultation documents and supplementary specifications are available in the official language of the country.
More from Peru
Implementation of an e-learning learning management system for the National Digital Talent Platform
Methodology for the evaluation of the curricular design of the EESP. Action 4.1
Methodology for the design and management of ESP optimisation plans – Action 3.1
Design and construction of the integral drinking water and sewerage system of Zarumilla and Aguas Verdes – Stage 03, Section 3.1
More in Educational infrastructure
Provision of equipment, appliances and kitchen utensils for educational centers
Acquisition of pedagogical kits for the schools of the PAPDEF project and public schools
Contracting of a company for the integral execution of the construction works of the Dr. Francisco de Paula Pinheiro State School