Technical counterpart for the processing of the environmental qualification resolution (RCA) for the Coquimbo desalination plant
Opportunity details
Description
The Inter-American Development Bank (IDB) is calling on specialized firms to act as a technical-environmental counterpart to the Ministry of Public Works / General Directorate of Concessions (MOP/DGC) of Chile. The main objective is to review and control the quality of the work carried out by the consultancy in charge of preparing Addendum No. 2 and its successive iterations, guaranteeing the obtaining of a favorable Environmental Qualification Resolution (RCA) for the project.
1. Quality control and consistency of the file
- Responses to ICSARA: Verification that the responses to the Consolidated Report on the Request for Clarifications, Rectifications and/or Extensions No. 2 are well-founded, sufficient and technically verifiable.
- Internal consistency: Exhaustive review to avoid contradictions between the project description, the areas of influence, the impacts evaluated, the proposed measures, the cartography and the annexes.
- Minutes of observations: Preparation of formal reports for the MOP that prioritize critical gaps and define the requirements for improvement in drafting, traceability and technical evidence.
2. Coordination and mitigation of regulatory risks
- Articulation of actors: Management of follow-up meetings and technical coordination between the MOP/DGC, the consultancy responsible for the EIA and the public services with environmental competence.
- Early warnings: Timely identification of technical, legal, and schedule risks that may affect the flow of assessment or approval in the Environmental Impact Assessment System (SEIA).
- Deadline control: Supervision of delivery milestones according to the contractual schedule to ensure the available pronouncement times of the MOP.
3. Closing addenda and post-entry support
- Consolidated review: Final verification of the completeness of the file of Addendum No. 2 prior to its formal entry and preparation of the draft of the ex officio conformity for the Tax Inspector.
- Technical accompaniment: Continuous support to the MOP/DGC during the post-entry evaluation phase to resolve omissions or additional institutional requirements.
- Closure analysis: Technical review of the Consolidated Assessment Report (ICE) and detailed analysis of the environmental resolution (RCA) once issued.
Note: Interested companies should review the requirements on the BEO Bidder Portal.
More in Project impact
Consultancy to Conduct Evaluation of the Zones of Special Operations in Jamaica
Consultancy for the Realization of the Integrated Evaluation Study of the Project "Strengthening Sustainable Value Chains in the Amazon - PRS Amazonia" (BR-T1462)
Loss Mitigation Analytics and DSM Frameworks Consultancy
Review and revalidation of the priorities of the expansion works of the High Voltage Transmission System of Argentina